BLOCK LIFTING SYSTEM WITH MONORAIL TROLLEYS
- Available as two-rail system (30 m installation) and four-rail system (60 m installation)
- The 60 m block lifting unit consists of 4 single-rail trolleys, 2 block grippers, a central control system and a power supply system for the electric supply of the single-rail trolleys and block grippers
- For the tranverse movement the crane unit runs in existing crane runways
- The drives for the tranverse movement are frequency-controlled
- A laser distance sensing system is provided for each monorail trolley
- The monorail trolleys are electrically synchronized
- Compared to overhead crane runways, the aforementioned system generates much less roof load
- For block lengths of approx. 45 m and longer, two block grippers with separate transportation systems are installed as a rule
- These systems can be operated synchronously as well as in separate cross drive
- Laser measuring systems ensure maximum precision in positioning